Public Notice: Temporary Closure – 01 Market Junction
The public is hereby informed that the previous advisory issued on 6 April 2026 regarding works at the 01 Market Junction has been revised. This amendment follows initial implementation findings of the Traffic Management Plan, which confirmed that vehicles cannot safely pass along the roadside adjacent to the worksite due to construction limits.
In light of the above, the following measures will apply:
- Traffic Advisory
The road junction will be fully closed to all vehicular traffic during the construction period.
Vehicles travelling to and from 01 Market and the Tasahe B area are advised to use 02 Road as the designated temporary diversion route.
For safety reasons, heavily loaded trucks are strictly prohibited from using the Bailey bridge. - Safety Measures
The work area at the 01 Junction will be securely barricaded to ensure public safety.
Appropriate traffic signs and safety devices will be installed prior to the commencement of works to guide both motorists and pedestrians. - Pedestrian Access
Designated pedestrian walkways and crossing points will be provided.
Safety Officers and Traffic Controllers will be deployed on-site to assist pedestrians and motorists, ensuring safety and maintaining an orderly flow of movement. - Traffic Management Plan
The Traffic Management Plan is attached for reference. Additional signage may be installed as required, depending on actual site conditions.
Please note that the work schedule may be adjusted subject to weather conditions.
See Traffic Management Plan.
For enquiries, please contact:
- MID Safeguards-Roxsley Basil at 7582239 or email address RBasil@mid.gov.sb;
- Consultant’s Communications Officer, Lawrence Nodua on mobile number 7252525 or email lnodua@lmcp.com.sb
- CSC Safeguards, Jennifer S Kikolo on mobile number 7914014 or email jsikele@lmcp.com.sb
- Tioko Etupioh, CCECC Community Liaison Officer at mobile number 7680708
- Qi Rongbao, CCECC Authorized Management Representative email address qirongbaoccecc@gmail.com
- David Gange, CCECC Safeguard Specialist/ EHS Manager at 7376307 or dgange813ccecc@gmail.com
We appreciate your understanding and support as we continue to upgrade our city’s road infrastructure.
Thank you
This Public Notice is authorized by:
__________________________________________________
Mike Qaqara
Deputy Secretary Technical